Silicon Valley Power - City of Santa Clara (SVP)

Phase Shifting Transformer

scroll down

Client: Silicon Valley Power – City of Santa Clara (SVP)

Testing & Commissioning of a 420MVA phase shifting transformer, testing of all CT and PT circuits, testing of all AC/DC control circuits and protective relays associated with the PST and 230kV lines between three substations. Project required close coordination with SVP and PG&E protection engineers responsible for interconnection between the two service areas. Project also required careful coordination with project managers tasked with maintaining reliable service during 2016 Super bowl activities at nearby Levi stadium. Unit was placed in service on schedule.